Work Completed Completed base asphalt paving for the future southbound lanes Switched southbound traffic onto the new lanes except at[...]
South Section: Lake Cook Road to Deerfield Parkway
Project Update Video
Check out the video for an update of the project’s progress.
New Staging Pattern
Traffic will be shifted to a new staging pattern on Weiland Road from Deerfield Parkway to Woodstone Drive tomorrow, September[...]
Project Update 9/17/20
Work Completed The storm sewer installation, earth excavation and stone base have been completed for the future southbound lanes from[...]
Project Update 8/14/20
Work Completed The pavement removal from Woodstone Drive to Deerfield Parkway has been completed. The contractor has completed installation of[...]
Project Update 7/13/2020
Stage 1 pavement work has been completed, and the traffic has been moved to the new pavement. The new sidewalk[...]
Project Update 6/19/20 and Upcoming New Lane Configuration
The contractor completed the concrete work on the east side of Weiland Rd this week in preparation for the traffic[...]
Visit the Gallery Page
Visit the Gallery Page to view drone videos, progress photos, and the construction site webcam.
Project Update 6/3/2020
Last week the contractor completed excavation and placement of the stone base for the roadway on the east side. The[...]
Project Update 5/19/2020
Work continued on the concrete curb and asphalt pavement installations. The new pavement base has been installed from Woodstone Drive[...]