Work continued on the concrete curb and asphalt pavement installations. The new pavement base has been installed from Woodstone Drive[...]
Update
Project Update 5/19/2020
The contractor’s progress has been slowed due to the recent rainfall. The contractor has removed the majority of existing pavement,[...]
Project Update 5/11/2020
Last week’s work included northbound lane pavement removal, installation of temporary barrier wall, and old street lighting removal. This week[...]
Project Update 5/11/2020
Last week the contractor continued to excavate and place stone base for the roadway from Pauline Ave. to Newtown Dr.[...]
Project Update 4/29/2020
Last week the contractor completed pavement removal on the east side of Weiland, started earth excavation and stone base placement,[...]
Project Update 4/28/2020
Last week the contractor continued working on the temporary lighting and traffic signals, as well as installing storm sewer and[...]
Project Update 4/17/2020
The roadway has been temporarily patched where the box culvert was constructed at the Aptakisic Creek. There will be a[...]
Project Update 4/17/2020
The new temporary traffic signal is now turned on at the Aptakisic Junior High School South Entrance and the old[...]
Notice – Temporary Signal Turn-On
A new traffic signal will be activated at the Aptakisic Junior High School SOUTH entrance on Wednesday, April 15th. This[...]
Project Update 4/2/2020
Temporary street lighting and traffic signal installation is ongoing. These temporary installations will replace the existing street lights and traffic[...]