  • The final asphalt surface has been paved on both Weiland Rd and Aptakisic Rd. All lanes are now open.
  • Striping of the permanent pavement markings (to replace the abbreviated temporary tape in place now) is scheduled to begin next week.
  • New light poles have been installed and are scheduled to be turned on next week.
  • Removal of temporary wood light poles will follow.
  • Trees and perennial plants are expected to be planted in the landscaped medians at the end of August.
  • Sodding is on hold during the summer months, waiting for more suitable temperatures.
  • Activation of the new traffic signals is scheduled for the week of August 30th.