Weiland South

Work Completed

  • The new traffic signals at Pauline and Weiland Road were activated on Wednesday, 3/31/21, and removal of the temporary signals began.
  • Crews installed the chain link fence at the soccer fields south of Pauline Ave.

Upcoming Work

  • The contractor will be mobilizing within the next couple of weeks to resume work on the permanent landscaping, complete tree planting, place permanent pavement markings, and complete other miscellaneous items.
  • Expect daily lane closures, workers, and machinery.

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.