The contractor completed work to allow the activation of the temporary signals at Aptakisic this week. The installation of the[...]
Blog - Archive: June, 2020
Project Update 6/19/20 and Upcoming New Lane Configuration
The contractor completed the concrete work on the east side of Weiland Rd this week in preparation for the traffic[...]
Visit the Gallery Page
Visit the Gallery Page to view drone videos and progress photos.
Visit the Gallery Page
Visit the Gallery Page to view drone videos, progress photos, and the construction site webcam.
Project Update 6/3/2020
Last week the contractor continued with removal of the curb, driveways, and sidewalks and began the installation of storm sewer[...]
Project Update 6/3/2020
Last week the contractor completed excavation and placement of the stone base for the roadway on the east side. The[...]