Slide 1
Weiland Road
Improvements

The Weiland Road Improvement Project will increase highway user safety, improve capacity and operation, replace aging infrastructure, and enhance the regional roadway network.

Slide2
Weiland Road
Improvements

The Weiland Road Improvement Project is split in two sections. The South Section includes work on Weiland from north of Lake Cook Road (Woodstone Drive) to south of Deerfield Parkway.

Slide3
Weiland Road
Improvements

The Weiland Road Improvement Project is split in two sections. The North Section includes work on Weiland Road from Deerfield Parkway to Aptakisic Road, and Aptakisic Road from Joseph Court to Bond Street.

previous arrowprevious arrow
next arrownext arrow
Shadow

Current Project Information.

The South Section is approximately 99% complete
The North Section is 90% complete.