Visit the Gallery Page

Visit the Gallery Page to view drone videos and progress photos.

More

Visit the Gallery Page

Visit the Gallery Page to view drone videos, progress photos, and the construction site webcam.

More

Project Update 6/3/2020

Last week the contractor continued with removal of the curb, driveways, and sidewalks and began the installation of storm sewer on the east side at Abbott Ct. This week the storm sewer installation continues, and work has begun on the retaining wall between Depot Place and Old Weiland Road. Stay tuned to the website for… Continue reading

More

Project Update 6/3/2020

Last week the contractor completed excavation and placement of the stone base for the roadway on the east side.  The concrete curb was also poured from Newtown Dr to Deerfield Pkwy and at some driveways. Permanent lighting system installation is ongoing. Construction is very active this week with concrete work and asphalt placement occurring. The… Continue reading

More

Project Update 5/19/2020

Work continued on the concrete curb and asphalt pavement installations. The new pavement base has been installed from Woodstone Drive to Newtown Drive. Storm sewer installations have been completed on the east side work zone. Street light foundations are being installed from Woodstone Drive going north. Traffic signal foundations were also installed at Pauline Avenue. … Continue reading

More

Project Update 5/19/2020

The contractor’s progress has been slowed due to the recent rainfall.  The contractor has removed the majority of existing pavement, curb, and driveways on the east side of the road in preparation for the new storm sewer installation. Storm sewer work will continue for the next couple of weeks, followed by grading. Work is also… Continue reading

More

Project Update 5/11/2020

Last week’s work included northbound lane pavement removal, installation of temporary barrier wall, and old street lighting removal. This week the contractor will continue removing the northbound curb, pavement, driveways, and storm sewer in preparation of the new installations. Earth excavation will start in this area as well, and work on the retaining wall just… Continue reading

More

Project Update 5/11/2020

Last week the contractor continued to excavate and place stone base for the roadway from Pauline Ave. to Newtown Dr. Storm sewer installations continued from Newtown Dr. to the north, and curb and gutter was installed from Pauline Ave. to Newtown Dr. on Thursday, May 7. This week the contractor is grading the stone base… Continue reading

More

Project Update 4/29/2020

Last week the contractor completed pavement removal on the east side of Weiland, started earth excavation and stone base placement, and continued with storm sewer installations. Traffic was moved over the newly construction box culvert at Marvins Way, allowing the contractor access to the entire east side construction zone.   This week the contractor continues… Continue reading

More

Project Update 4/28/2020

Last week the contractor continued working on the temporary lighting and traffic signals, as well as installing storm sewer and excavating for temporary pavement. The temporary pavement placement was completed yesterday, 4/27/20, and traffic is scheduled to be moved tomorrow, 4/29/20, depending on the weather conditions. Work will continue on pavement removals, earth excavation, and… Continue reading

More