New Staging Pattern!

Aptakisic Road from Joseph Court to Industrial Drive will enter the new construction staging pattern today as part of the reconstruction of Weiland and Aptakisic Roads. The new traffic pattern will reduce the number of through lanes to 1 in each direction to allow the reconstruction of the roadway. New rail crossing signals will be… Continue reading

More

Project Update 7/13/2020

The contractor installed storm sewer south of Abbott Court, completed work on the retaining wall south of Old Weiland Road, and continued earth excavation and stone base placement this past week. Tuesday, July 14 –  the contractor is scheduled to activate the temporary traffic signals at Aptakisic & Weiland and Aptakisic & Bond.  With the… Continue reading

More

Project Update 7/13/2020

Stage 1 pavement work has been completed, and the traffic has been moved to the new pavement. The new sidewalk along the east side (northbound lanes) is installed, and temporary seeding has been placed.  The light pole foundations and electrical wiring have been installed for the northbound street lighting, and the driveway work on this… Continue reading

More

Project Update 6/19/20

The contractor completed work to allow the activation of the temporary signals at Aptakisic this week. The installation of the storm sewer continued south of Abbott Ct. The work on the retaining wall south of Old Weiland Rd was also completed. Next week excavation and storm sewer installation will continue. Stay tuned to the website… Continue reading

More

Project Update 6/19/20 and Upcoming New Lane Configuration

The contractor completed the concrete work on the east side of Weiland Rd this week in preparation for the traffic switch scheduled for Monday, June 22, 2020. The driveways on the east side and the topsoil placement were also completed. The retaining walls at the culvert south of Marvins Way have had decorative stain applied… Continue reading

More

Visit the Gallery Page

Visit the Gallery Page to view drone videos and progress photos.

More

Visit the Gallery Page

Visit the Gallery Page to view drone videos, progress photos, and the construction site webcam.

More

Project Update 6/3/2020

Last week the contractor continued with removal of the curb, driveways, and sidewalks and began the installation of storm sewer on the east side at Abbott Ct. This week the storm sewer installation continues, and work has begun on the retaining wall between Depot Place and Old Weiland Road. Stay tuned to the website for… Continue reading

More

Project Update 6/3/2020

Last week the contractor completed excavation and placement of the stone base for the roadway on the east side.  The concrete curb was also poured from Newtown Dr to Deerfield Pkwy and at some driveways. Permanent lighting system installation is ongoing. Construction is very active this week with concrete work and asphalt placement occurring. The… Continue reading

More

Project Update 5/19/2020

Work continued on the concrete curb and asphalt pavement installations. The new pavement base has been installed from Woodstone Drive to Newtown Drive. Storm sewer installations have been completed on the east side work zone. Street light foundations are being installed from Woodstone Drive going north. Traffic signal foundations were also installed at Pauline Avenue. … Continue reading

More