New Staging Pattern

Traffic will be shifted to a new staging pattern on Weiland Road from Deerfield Parkway to Woodstone Drive tomorrow, September 23rd. The southbound lanes will be placed on the newly constructed pavement, and the northbound lanes will stay in place.  This shift will allow the contractor to complete the work in between the northbound and… Continue reading

More

Project Update 9/17/2020

Work Completed Weiland Road – The contractor has completed the storm sewer up to Old Weiland Rd, installed street lighting and traffic signal items from Deerfield Parkway to Abbott as well as installed the asphalt base to Depot Place. Aptakisic Road – The contractor has completed pavement removal on the north and south sides of… Continue reading

More

Project Update 9/17/20

Work Completed The storm sewer installation, earth excavation and stone base have been completed for the future southbound lanes from Deerfield Parkway to Woodstone Drive. The new curb & gutter and asphalt pavement was installed the last week of August from Deerfield Parkway to Newtown. The contractor has started grading behind the curb & gutter… Continue reading

More

Project Update 8/14/2020

Work Completed Weiland Road – The stone base was installed and prepared for curb installation from Deerfield Parkway north to Depot Place. The curb was installed, as well as some driveways last week. This week installation of the new asphalt pavement began in the same area. Traffic signal and street light foundation and underground wiring… Continue reading

More

Project Update 8/14/20

Work Completed The pavement removal from Woodstone Drive to Deerfield Parkway has been completed. The contractor has completed installation of 95% of the new storm sewer system and installed relocated water main in the Newtown area. The contractor has continued work on the earth excavation from Deerfield Parkway to Newtown. Installation of the stone base… Continue reading

More

New Staging Pattern!

Aptakisic Road from Joseph Court to Industrial Drive will enter the new construction staging pattern today as part of the reconstruction of Weiland and Aptakisic Roads. The new traffic pattern will reduce the number of through lanes to 1 in each direction to allow the reconstruction of the roadway. New rail crossing signals will be… Continue reading

More

Project Update 7/13/2020

The contractor installed storm sewer south of Abbott Court, completed work on the retaining wall south of Old Weiland Road, and continued earth excavation and stone base placement this past week. Tuesday, July 14 –  the contractor is scheduled to activate the temporary traffic signals at Aptakisic & Weiland and Aptakisic & Bond.  With the… Continue reading

More

Project Update 7/13/2020

Stage 1 pavement work has been completed, and the traffic has been moved to the new pavement. The new sidewalk along the east side (northbound lanes) is installed, and temporary seeding has been placed.  The light pole foundations and electrical wiring have been installed for the northbound street lighting, and the driveway work on this… Continue reading

More

Project Update 6/19/20

The contractor completed work to allow the activation of the temporary signals at Aptakisic this week. The installation of the storm sewer continued south of Abbott Ct. The work on the retaining wall south of Old Weiland Rd was also completed. Next week excavation and storm sewer installation will continue. Stay tuned to the website… Continue reading

More

Project Update 6/19/20 and Upcoming New Lane Configuration

The contractor completed the concrete work on the east side of Weiland Rd this week in preparation for the traffic switch scheduled for Monday, June 22, 2020. The driveways on the east side and the topsoil placement were also completed. The retaining walls at the culvert south of Marvins Way have had decorative stain applied… Continue reading

More