Notice – Temporary Signal Turn-On

A new traffic signal will be activated at the Aptakisic Junior High School SOUTH entrance on Wednesday, April 15th. This signal will take the place of the existing signal at the NORTH entrance, which will be removed. There will be new pavement striping on Weiland Road to accommodate the new location of the signal, as… Continue reading

More

Project Update 4/2/2020

Temporary street lighting and traffic signal installation is ongoing. These temporary installations will replace the existing street lights and traffic signals (at Weiland Rd & Aptakisic Junior High, Weiland Rd & Aptakisic Rd and Aptakisic Rd & Bond St) during construction. Temporary traffic signal installation at Weiland Rd & Aptakisic Rd Utility companies also continue… Continue reading

More

Project Update 4/2/2020

The concrete work for the culvert and retaining walls at Aptakisic Creek is complete, and the railing is being installed. The decorative stone pattern for the walls will be colored to look like natural stone. Railing Installation Storm sewer lateral work has resumed on the east side of Weiland Rd. This work will connect pipe… Continue reading

More

Project Update 3/20/2020

Installation of the temporary street lighting and temporary traffic signals is ongoing and will continue for the next few weeks. Erosion control installation has begun and will continue into next week. Utility companies continue to relocate their facilities throughout the site. Please drive carefully through the construction zone, refrain from cellphone use, and watch for… Continue reading

More

Project Update 3/20/2020

Construction continues on the Aptakisic Creek culvert with work focused on the poured in place headwall and retaining walls. Work will wrap up on the culvert and retaining walls next week, with cleanup and filling scheduled for the following week. Pavement, curb, and sidewalk removal is ongoing and will continue into next week, followed by… Continue reading

More

Project Update 3/12/2020

Work on the temporary street lighting continues on Weiland and Aptakisic. Temporary pavement has been installed at the railroad tracks to allow for future staging once work begins. Please drive carefully through the construction zone and watch for workers and equipment.

More

Project Update 3/12/2020

Traffic has been moved onto the temporary pavement (same configuration as last fall) to allow the resumption of work on the east side of the road. Excavation for the road bed and storm sewer installation are ongoing. Work continues on the Aptakisic Creek box culvert on the west side with the forming of the retaining… Continue reading

More

Lane Closure

Today, 3/9, there will be a westbound lane closure on Aptakisic Road between 9:00 am and 3:00 pm. Tuesday, 3/10, there will be lane closures on the inside eastbound and westbound lanes on Aptakisic Road between 9:00 am and 3:00 pm.

More

Project Update 3/5/2020

Next week (March 9th) traffic will be shifted back to the Stage 1 configuration from last fall. This shift will allow work to resume on the east side of the road. Storm sewer installation, earth excavation, and road building operations will resume. Traffic staging is weather dependent. Please drive carefully through the construction zone and… Continue reading

More

Public Open House Materials

Thank you to all those who came out to the Public Open House on March 4, 2020. Below are links to all of the exhibits that were on display at the meeting. Schedule Striping Plans Typical Sections Landscaping Plans Exhibit – Deerfield Parkway to Apatakisic Road If you have any questions or comments about the… Continue reading

More