    • Nicor is completing the installation of the new gas main and removal of the old main.
    • Storm sewer installations are scheduled to begin next week.
    • Work on the new box culvert at Aptakisic Creek is also scheduled to begin later this week or next week. This work is dependent on the weather and flows in creek.