Project Update 9/17/20

Work Completed
The storm sewer installation, earth excavation and stone base have been completed for the future southbound lanes from Deerfield Parkway to Woodstone Drive. The new curb & gutter and asphalt pavement was installed the last week of August from Deerfield Parkway to Newtown. The contractor has started grading behind the curb & gutter in preparation for path installation on the west side. Side street pavement has been removed to allow preparation for the installation of the new pavement as well as driveway work at various locations.
Installation of the remaining south bound curb from Newtown to Woodstone Drive was completed on 9/14/20, and the stone base prepared for the placement of the asphalt pavement.

Placing road fabric and aggregate base on the west side of Weiland Rd south of the paving operation and continued paving (South Section)
Placing road fabric and aggregate base on the west side of Weiland Rd south of the paving operation and continued paving (South Section)
Placing road fabric and aggregate base on the west side of Weiland Rd south of the paving operation and continued paving (South Section)
Paving on the west side of Weiland Rd (South Section)

Work Scheduled
Today, the first lifts of asphalt are being placed from Newtown to Woodstone Dr and are anticipated to be completed 9/21/20 weather dependent.
Week of 9/21/20
Work will continue on adjustments of underground installations as well as street lighting work. The new topsoil will be placed and followed by the installation of the seeding. Work on the west side path will also resume.

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 

Visit the Gallery Page for progress photos.