Project Update 8/26/19

Ongoing Work

  • Relocation of existing utilities in preparation of the widened road. Once complete, work will continue on the roadway.
  • Removal of old light poles.
  • Detention basin excavation.
  • Detention Basin Excavation

Completed Work

  • Temporary lighting has been has been installed and activated.
  • Temporary Lighting

  • Temporary pavement has been installed on the west side of Weiland Rd. and north side of Pauline Ave. to accommodate Stage 1 Construction traffic.
  • Temporary Pavement

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.

Visit the Gallery Page for construction site webcam and additional photos.