Project Update 8/14/2020

Work Completed
Weiland Road – The stone base was installed and prepared for curb installation from Deerfield Parkway north to Depot Place. The curb was installed, as well as some driveways last week. This week installation of the new asphalt pavement began in the same area. Traffic signal and street light foundation and underground wiring were also installed in various locations.
Aptakisic Road – Work included the railroad installing temporary crossing gates that will allow lanes to be moved to build the new roadway. Pavement removal has also begun.

Work Scheduled
Weiland Road – Complete asphalt pavement base layers from Deerfield Parkway to Depot Place. Excavate and prepare for the new sidewalk, and install underground items and foundations for the street lighting and traffic signals.
Aptakisic Road – Pavement removal will continue. Storm sewer installations will begin the week of 8/17. Street lighting and traffic signal work will continue.

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 