Project Update 8/14/20

Work Completed
The pavement removal from Woodstone Drive to Deerfield Parkway has been completed. The contractor has completed installation of 95% of the new storm sewer system and installed relocated water main in the Newtown area. The contractor has continued work on the earth excavation from Deerfield Parkway to Newtown. Installation of the stone base has followed in these areas as well. Existing fences have been removed in specific areas with temporary fencing installed to allow utility work.

Work Scheduled
Stone base installation will continue in preparation for the installation of the new curb and gutter on the northern section. This work is anticipated to occur the week of 8/17, weather dependent. The new asphalt pavement will follow the curb placement after the required curing period, allowing the concrete to get to full strength.