Last week the contractor completed excavation and placement of the stone base for the roadway on the east side.  The concrete curb was also poured from Newtown Dr to Deerfield Pkwy and at some driveways. Permanent lighting system installation is ongoing.

Construction is very active this week with concrete work and asphalt placement occurring. The contractor is pouring sidewalk and driveways and placing the asphalt base for the roadway.  It is expected that the asphalt and concrete work will continue this week up to the north end of the project at Deerfield Parkway.  There will be intermittent closures of Newtown Dr. with flaggers as the asphalt is paved through the intersection. Please utilize Pope Blvd. or Pauline Ave during these closures.

Paving Paving

Sidewalk Forms Pouring Sidewalk Concerete
Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 