Project Update 6/19/20 and Upcoming New Lane Configuration

The contractor completed the concrete work on the east side of Weiland Rd this week in preparation for the traffic switch scheduled for Monday, June 22, 2020. The driveways on the east side and the topsoil placement were also completed. The retaining walls at the culvert south of Marvins Way have had decorative stain applied to them and are now complete.
On Monday, the contractor will be placing temporary seeding and erosion control blanket on the east side in advance of the traffic staging switch. The traffic staging will result in a “split” stage with the northbound lane on the new pavement and the south bound lane staying where it is currently at. This work is weather dependent.

Check out the below video showing the upcoming split lane configuration.

 

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 

Visit the Gallery Page for construction site webcam.