Project Update 5/19/2020

The contractor’s progress has been slowed due to the recent rainfall.  The contractor has removed the majority of existing pavement, curb, and driveways on the east side of the road in preparation for the new storm sewer installation. Storm sewer work will continue for the next couple of weeks, followed by grading. Work is also scheduled to begin on the retaining wall at the detention basin just south of Old Weiland Road.
Pavement Removal Pavement Removal

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 