Last week the contractor continued to excavate and place stone base for the roadway from Pauline Ave. to Newtown Dr. Storm sewer installations continued from Newtown Dr. to the north, and curb and gutter was installed from Pauline Ave. to Newtown Dr. on Thursday, May 7.

This week the contractor is grading the stone base from Pauline Ave. to Newtown Dr. in anticipation of the installation of the permanent asphalt pavement scheduled for Tuesday or Wednesday this week (weather dependent).

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 