Project Update 4/29/2020

Last week the contractor completed pavement removal on the east side of Weiland, started earth excavation and stone base placement, and continued with storm sewer installations. Traffic was moved over the newly construction box culvert at Marvins Way, allowing the contractor access to the entire east side construction zone.

 Pavement Removal Pavement Removal

This week the contractor continues earth excavation and stone base placement and installation of storm sewer. The new north bound curb and gutter was poured Monday, 4/27/20 from north of Woodstone to Pauline Ave. Additional concrete work is scheduled for the rest of the week as well as grading operations.