Project Update 4/2/2020

The concrete work for the culvert and retaining walls at Aptakisic Creek is complete, and the railing is being installed. The decorative stone pattern for the walls will be colored to look like natural stone.

Railing Installation
Railing Installation

Storm sewer lateral work has resumed on the east side of Weiland Rd. This work will connect pipe from the larger structures installed last year to smaller ones in the new curb areas for drainage. This work will progress from the south limit across from Woodstone Dr to the north.

Excavation for the roadway and placement of the stone base on the east side is expected to start next week. The contractor has been crushing and processing recycled concrete and asphalt to reuse for the stone base. The asphalt recycling is being done onsite at a staging area by the detention pond.

Asphalt Recycling Asphalt Grinding
Asphalt Recycling

Please drive carefully through the construction zone, refrain from cellphone use, and watch for workers and equipment.