The roadway has been temporarily patched where the box culvert was constructed at the Aptakisic Creek.  There will be a NEW TRAFFIC PATTERN STARTING MONDAY, APRIL 20th to shift traffic west at this location, weather pending.  Once the traffic shift is in place, work on the east side of Weiland Rd can be finished from north of Newtown Dr to Deerfield Pkwy.

Storm sewer pipe installation is complete on the east side of Weiland Rd from the south limit to Newtown Dr.  This work includes installing smaller pipes from the larger structures installed last year to smaller ones in the new curb areas for drainage. This work will continue north of Newtown Dr next week.

Excavation for the roadway and placement of the stone base has started on the east side of Weiland Rd and will continue north.  Placement of concrete curb is also expected to start later next week.

Please drive carefully through the construction zone, refrain from cellphone use, and watch for workers and equipment.