Project Update 12/23/19

  • Storm sewer installation on the east side of Weiland Rd is finished for the year. The large diameter main line has been completed and connected to the detention basin on the east side between Pauline Ave. and Pope Blvd. The detention basin drains to the Aptakisic Creek. The disturbed areas will be covered by a temporary seed and erosion control blanket through the winter. In the Spring, new curb inlets will be installed and connected to the storm sewer system, followed by construction of the new roadway.
  • The retaining wall on the east side of the box culvert has been completed. The stone pattern will be stained next year to resemble natural stone.
  • Temporary pavement has also been installed, and traffic has been moved to the east side at the box culvert. Work on the west half of the box culvert started today and will continue through the winter, weather permitting.

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 

Visit the Gallery Page for construction site webcam.