Project Update 11/11/19

  • Storm sewer installation has continued on the east side of the roadway south of Newtown Drive. The storm sewer crew has moved further south past an area where another crew is relocating the existing water main and sanitary sewer and will be crossing Pauline Ave. today, 11/11. Pauline Ave. will remain open to traffic with flaggers directing traffic around the work zone. The storm sewer work will continue south of Pauline Ave the remainder of the week.
  • The water main replacement is almost complete on the east side of the roadway from Pauline Ave to north of Pope Blvd. The new main is currently being filled with water and tested before the final connections are made.
  • Work on the east half of the box culvert crossing at Aptakisic Creek had been postponed due to weather and high water levels at the Creek, but resumed this past week. Concrete placement for the soldier pile wingwall is expected soon, which will include a decorative formliner.

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 

Visit the Gallery Page for construction site webcam.