  • Nicor/NPL is continuing removal of the old gas main and restoring the area. They are scheduled to complete this work early next week.
  • Once the utility relocation work is complete, the roadway work will resume.
  • The contractor has begun relocating water main in preparation for the installation of the 4.5′ diameter storm sewer pipe. The installation is scheduled to begin 10/4/19.
  • The water diversion structure (cofferdam) will be reinstalled Friday, 10/4/19. Then the existing box culvert will be removed at Aptakisic Creek. During this work, the area south of Marvin’s Way will be congested with equipment and workers. Please proceed in this area with extra caution to keep everyone safe.

Stay tuned to the website for future updates.

Please drive carefully through the construction zone and watch for workers and equipment.

 