Project Update 10/3/19

Nicor/NPL is continuing removal of the old gas main and restoring the area. They are scheduled to complete this work early next week. Once the utility relocation work is complete, the roadway work will resume. The contractor has begun relocating water main in preparation for the installation of the 4.5′ diameter storm sewer pipe. The… Continue reading

More

Project Update 9/25/19

Nicor is completing the installation of the new gas main and removal of the old main. Storm sewer installations are scheduled to begin next week. Work on the new box culvert at Aptakisic Creek is also scheduled to begin later this week or next week. This work is dependent on the weather and flows in… Continue reading

More

New Traffic Pattern Starting Thursday, 8/29/19. Be Alert!

Traffic will be shifted onto the temporary pavement along the west side of Weiland Rd starting Thursday, 8/29/19. This shift will allow construction of the box culvert crossing at Aptakisic Creek to begin.   Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.

More

Project Update 8/26/19

Ongoing Work Relocation of existing utilities in preparation of the widened road. Once complete, work will continue on the roadway. Removal of old light poles. Detention basin excavation. Completed Work Temporary lighting has been has been installed and activated. Temporary pavement has been installed on the west side of Weiland Rd. and north side of… Continue reading

More

Project Update 8/13/19

Ongoing Work Relocation of existing utilities in preparation of the widened road. Once complete, work will continue on the roadway. Installation of temporary lighting. Completed Work The temporary pavement has been installed. Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.

More