Project Update 4/17/2020

The roadway has been temporarily patched where the box culvert was constructed at the Aptakisic Creek.  There will be a NEW TRAFFIC PATTERN STARTING MONDAY, APRIL 20th to shift traffic west at this location, weather pending.  Once the traffic shift is in place, work on the east side of Weiland Rd can be finished from… Continue reading

More

Project Update 4/2/2020

The concrete work for the culvert and retaining walls at Aptakisic Creek is complete, and the railing is being installed. The decorative stone pattern for the walls will be colored to look like natural stone. Railing Installation Storm sewer lateral work has resumed on the east side of Weiland Rd. This work will connect pipe… Continue reading

More

Project Update 3/20/2020

Construction continues on the Aptakisic Creek culvert with work focused on the poured in place headwall and retaining walls. Work will wrap up on the culvert and retaining walls next week, with cleanup and filling scheduled for the following week. Pavement, curb, and sidewalk removal is ongoing and will continue into next week, followed by… Continue reading

More

Project Update 3/12/2020

Traffic has been moved onto the temporary pavement (same configuration as last fall) to allow the resumption of work on the east side of the road. Excavation for the road bed and storm sewer installation are ongoing. Work continues on the Aptakisic Creek box culvert on the west side with the forming of the retaining… Continue reading

More

Project Update 3/5/2020

Next week (March 9th) traffic will be shifted back to the Stage 1 configuration from last fall. This shift will allow work to resume on the east side of the road. Storm sewer installation, earth excavation, and road building operations will resume. Traffic staging is weather dependent. Please drive carefully through the construction zone and… Continue reading

More