Project Update 9/17/20
Work Completed The storm sewer installation, earth excavation and stone base have been completed for the future southbound lanes from Deerfield Parkway to Woodstone Drive. The new curb & gutter and asphalt pavement was installed the last week of August from Deerfield Parkway to Newtown. The contractor has started grading behind the curb & gutter… Continue reading
14 Aug
2020
Project Update 8/14/20
Work Completed The pavement removal from Woodstone Drive to Deerfield Parkway has been completed. The contractor has completed installation of 95% of the new storm sewer system and installed relocated water main in the Newtown area. The contractor has continued work on the earth excavation from Deerfield Parkway to Newtown. Installation of the stone base… Continue reading
13 Jul
2020
Project Update 7/13/2020
Stage 1 pavement work has been completed, and the traffic has been moved to the new pavement. The new sidewalk along the east side (northbound lanes) is installed, and temporary seeding has been placed. The light pole foundations and electrical wiring have been installed for the northbound street lighting, and the driveway work on this… Continue reading
19 Jun
2020
Project Update 6/19/20 and Upcoming New Lane Configuration
The contractor completed the concrete work on the east side of Weiland Rd this week in preparation for the traffic switch scheduled for Monday, June 22, 2020. The driveways on the east side and the topsoil placement were also completed. The retaining walls at the culvert south of Marvins Way have had decorative stain applied… Continue reading
08 Jun
2020