Visit the Gallery Page

Visit the Gallery Page to view drone videos, progress photos, and the construction site webcam.

More

Project Update 6/3/2020

Last week the contractor completed excavation and placement of the stone base for the roadway on the east side.  The concrete curb was also poured from Newtown Dr to Deerfield Pkwy and at some driveways. Permanent lighting system installation is ongoing. Construction is very active this week with concrete work and asphalt placement occurring. The… Continue reading

More

Project Update 5/19/2020

Work continued on the concrete curb and asphalt pavement installations. The new pavement base has been installed from Woodstone Drive to Newtown Drive. Storm sewer installations have been completed on the east side work zone. Street light foundations are being installed from Woodstone Drive going north. Traffic signal foundations were also installed at Pauline Avenue. … Continue reading

More

Project Update 5/11/2020

Last week the contractor continued to excavate and place stone base for the roadway from Pauline Ave. to Newtown Dr. Storm sewer installations continued from Newtown Dr. to the north, and curb and gutter was installed from Pauline Ave. to Newtown Dr. on Thursday, May 7. This week the contractor is grading the stone base… Continue reading

More

Project Update 4/29/2020

Last week the contractor completed pavement removal on the east side of Weiland, started earth excavation and stone base placement, and continued with storm sewer installations. Traffic was moved over the newly construction box culvert at Marvins Way, allowing the contractor access to the entire east side construction zone.   This week the contractor continues… Continue reading

More