New Traffic Pattern Starting Thursday, 8/29/19. Be Alert!

Traffic will be shifted onto the temporary pavement along the west side of Weiland Rd starting Thursday, 8/29/19. This shift will allow construction of the box culvert crossing at Aptakisic Creek to begin.   Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.

More

Project Update 8/26/19

Ongoing Work Relocation of existing utilities in preparation of the widened road. Once complete, work will continue on the roadway. Removal of old light poles. Detention basin excavation. Completed Work Temporary lighting has been has been installed and activated. Temporary pavement has been installed on the west side of Weiland Rd. and north side of… Continue reading

More

Project Update 8/13/19

Ongoing Work Relocation of existing utilities in preparation of the widened road. Once complete, work will continue on the roadway. Installation of temporary lighting. Completed Work The temporary pavement has been installed. Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.

More

Project Update 7/24/19

Ongoing Work Relocation of existing utilities in preparation of the widened road. Excavations for temporary pavement and installation of storm sewer. Demolition of the 5 houses between Pauline Ave. and Pope Blvd. Completed Work The temporary traffic signal has been installed and activated. Erosion control measures have been installed to contain water and sediment to… Continue reading

More

Project Update 6/28/2019

Construction for the Weiland Road Improvements is scheduled to start Monday, July 8th. The contractor will start with pre-stage work, which includes installation of traffic control signs, erosion control measures, and tree protection, removals, and other preliminary work.

More