Project Update 5/19/2020

The contractor’s progress has been slowed due to the recent rainfall.  The contractor has removed the majority of existing pavement, curb, and driveways on the east side of the road in preparation for the new storm sewer installation. Storm sewer work will continue for the next couple of weeks, followed by grading. Work is also… Continue reading

More

Project Update 5/11/2020

Last week’s work included northbound lane pavement removal, installation of temporary barrier wall, and old street lighting removal. This week the contractor will continue removing the northbound curb, pavement, driveways, and storm sewer in preparation of the new installations. Earth excavation will start in this area as well, and work on the retaining wall just… Continue reading

More

Project Update 5/11/2020

Last week the contractor continued to excavate and place stone base for the roadway from Pauline Ave. to Newtown Dr. Storm sewer installations continued from Newtown Dr. to the north, and curb and gutter was installed from Pauline Ave. to Newtown Dr. on Thursday, May 7. This week the contractor is grading the stone base… Continue reading

More

Project Update 4/29/2020

Last week the contractor completed pavement removal on the east side of Weiland, started earth excavation and stone base placement, and continued with storm sewer installations. Traffic was moved over the newly construction box culvert at Marvins Way, allowing the contractor access to the entire east side construction zone.   This week the contractor continues… Continue reading

More

Project Update 4/28/2020

Last week the contractor continued working on the temporary lighting and traffic signals, as well as installing storm sewer and excavating for temporary pavement. The temporary pavement placement was completed yesterday, 4/27/20, and traffic is scheduled to be moved tomorrow, 4/29/20, depending on the weather conditions. Work will continue on pavement removals, earth excavation, and… Continue reading