22 Oct
2020
Project Update 10/22/2020
Work Completed Completed base asphalt paving for the future southbound lanes Switched southbound traffic onto the new lanes except at the location of the new Noise Abatement Wall Removed temporary pavement between the new northbound and southbound lanes, excavated and placed stone base for median and asphalt placement Poured median curb and gutters Placement of… Continue reading
08 Oct
2020
08 Oct
2020
22 Sep
2020
New Staging Pattern
Traffic will be shifted to a new staging pattern on Weiland Road from Deerfield Parkway to Woodstone Drive tomorrow, September 23rd. The southbound lanes will be placed on the newly constructed pavement, and the northbound lanes will stay in place. This shift will allow the contractor to complete the work in between the northbound and… Continue reading
17 Sep
2020
Project Update 9/17/2020
Work Completed Weiland Road – The contractor has completed the storm sewer up to Old Weiland Rd, installed street lighting and traffic signal items from Deerfield Parkway to Abbott as well as installed the asphalt base to Depot Place. Aptakisic Road – The contractor has completed pavement removal on the north and south sides of… Continue reading