Project Update 8/14/2020

Work Completed Weiland Road – The stone base was installed and prepared for curb installation from Deerfield Parkway north to Depot Place. The curb was installed, as well as some driveways last week. This week installation of the new asphalt pavement began in the same area. Traffic signal and street light foundation and underground wiring… Continue reading

More

New Staging Pattern!

Aptakisic Road from Joseph Court to Industrial Drive will enter the new construction staging pattern today as part of the reconstruction of Weiland and Aptakisic Roads. The new traffic pattern will reduce the number of through lanes to 1 in each direction to allow the reconstruction of the roadway. New rail crossing signals will be… Continue reading

More

Project Update 7/13/2020

The contractor installed storm sewer south of Abbott Court, completed work on the retaining wall south of Old Weiland Road, and continued earth excavation and stone base placement this past week. Tuesday, July 14 –  the contractor is scheduled to activate the temporary traffic signals at Aptakisic & Weiland and Aptakisic & Bond.  With the… Continue reading

More

Project Update 6/19/20

The contractor completed work to allow the activation of the temporary signals at Aptakisic this week. The installation of the storm sewer continued south of Abbott Ct. The work on the retaining wall south of Old Weiland Rd was also completed. Next week excavation and storm sewer installation will continue. Stay tuned to the website… Continue reading

More

Visit the Gallery Page

Visit the Gallery Page to view drone videos and progress photos.

More