Project Update 7/13/2020

Stage 1 pavement work has been completed, and the traffic has been moved to the new pavement. The new sidewalk along the east side (northbound lanes) is installed, and temporary seeding has been placed.  The light pole foundations and electrical wiring have been installed for the northbound street lighting, and the driveway work on this… Continue reading

More

Project Update 6/19/20

The contractor completed work to allow the activation of the temporary signals at Aptakisic this week. The installation of the storm sewer continued south of Abbott Ct. The work on the retaining wall south of Old Weiland Rd was also completed. Next week excavation and storm sewer installation will continue. Stay tuned to the website… Continue reading

More

Project Update 6/19/20 and Upcoming New Lane Configuration

The contractor completed the concrete work on the east side of Weiland Rd this week in preparation for the traffic switch scheduled for Monday, June 22, 2020. The driveways on the east side and the topsoil placement were also completed. The retaining walls at the culvert south of Marvins Way have had decorative stain applied… Continue reading

More

Visit the Gallery Page

Visit the Gallery Page to view drone videos and progress photos.

More

Visit the Gallery Page

Visit the Gallery Page to view drone videos, progress photos, and the construction site webcam.