Project Update 10/22/2020

Work Completed Completed base asphalt paving for the future southbound lanes Switched southbound traffic onto the new lanes except at the location of the new Noise Abatement Wall Removed temporary pavement between the new northbound and southbound lanes, excavated and placed stone base for median and asphalt placement Poured median curb and gutters Placement of… Continue reading

More

Project Update Video

Check out the video for an update of the project’s progress.

More

Project Update Video

Check out the video for an update of the project’s progress.

More

New Staging Pattern

Traffic will be shifted to a new staging pattern on Weiland Road from Deerfield Parkway to Woodstone Drive tomorrow, September 23rd. The southbound lanes will be placed on the newly constructed pavement, and the northbound lanes will stay in place.  This shift will allow the contractor to complete the work in between the northbound and… Continue reading

More

Project Update 9/17/2020

Work Completed Weiland Road – The contractor has completed the storm sewer up to Old Weiland Rd, installed street lighting and traffic signal items from Deerfield Parkway to Abbott as well as installed the asphalt base to Depot Place. Aptakisic Road – The contractor has completed pavement removal on the north and south sides of… Continue reading