Project Update 11/21/19

Storm sewer installation is ongoing. The storm sewer is being installed south of Pauline Ave. and will continue south and connect to the newly installed box culvert. The contractor is working on the south retaining wall at the box culvert. Temporary pavement will be placed over the culvert in anticipation of moving to the west… Continue reading

More

Project Update 11/11/19

Storm sewer installation has continued on the east side of the roadway south of Newtown Drive. The storm sewer crew has moved further south past an area where another crew is relocating the existing water main and sanitary sewer and will be crossing Pauline Ave. today, 11/11. Pauline Ave. will remain open to traffic with… Continue reading

More

Project Update 10/18/19

Installation of the 4.5′ diameter storm sewer has started from Aptakisic Creek south towards Newtown Drive. Trucks are parked on the east side of road within the park area to brace utility poles as this work passes by. Storm sewer installation crossing Newtown Drive will take place Thursday 10/17 and Friday 10/18. Installation will continue… Continue reading

More

Project Update 10/3/19

Nicor/NPL is continuing removal of the old gas main and restoring the area. They are scheduled to complete this work early next week. Once the utility relocation work is complete, the roadway work will resume. The contractor has begun relocating water main in preparation for the installation of the 4.5′ diameter storm sewer pipe. The… Continue reading

More

Project Update 9/25/19

Nicor is completing the installation of the new gas main and removal of the old main. Storm sewer installations are scheduled to begin next week. Work on the new box culvert at Aptakisic Creek is also scheduled to begin later this week or next week. This work is dependent on the weather and flows in… Continue reading