Check out the video for an update of the project’s progress.
Blog
New Staging Pattern
Traffic will be shifted to a new staging pattern on Weiland Road from Deerfield Parkway to Woodstone Drive tomorrow, September[...]
Project Update 9/17/2020
Work Completed Weiland Road – The contractor has completed the storm sewer up to Old Weiland Rd, installed street lighting[...]
Project Update 9/17/20
Work Completed The storm sewer installation, earth excavation and stone base have been completed for the future southbound lanes from[...]
Project Update 8/14/2020
Work Completed Weiland Road – The stone base was installed and prepared for curb installation from Deerfield Parkway north to[...]
Project Update 8/14/20
Work Completed The pavement removal from Woodstone Drive to Deerfield Parkway has been completed. The contractor has completed installation of[...]
New Staging Pattern!
Aptakisic Road from Joseph Court to Industrial Drive will enter the new construction staging pattern today as part of the[...]
Project Update 7/13/2020
The contractor installed storm sewer south of Abbott Court, completed work on the retaining wall south of Old Weiland Road,[...]
Project Update 7/13/2020
Stage 1 pavement work has been completed, and the traffic has been moved to the new pavement. The new sidewalk[...]
Project Update 6/19/20
The contractor completed work to allow the activation of the temporary signals at Aptakisic this week. The installation of the[...]