Check out the video for an update of the project’s progress.
Blog
Time-Lapse Video
This time-lapse video was taken from a camera at the NE corner of Weiland Rd & Pauline Ave that captured[...]
Project Update Video
Check out the video for an update of the project’s progress.
Project Update 1/7/2021
Weiland North The project is approximately 45% complete. Work Completed and Upcoming Weiland Road Traffic is currently driving on the[...]
Project Update 1/7/2021
Weiland South The project is approximately 95% complete. Work Completed Asphalt Surfacing was completed and all lanes opened to traffic[...]
Project Update 11/06/2020
Weiland North Work completed Weiland Rd – • Pavement removal in preparation for storm sewer installation • Electrical installations •[...]
Project Update 11/06/2020
Weiland South Work completed recently Excavation and stone base placement for the 8’ wide shared use path Installation of street[...]
Project Update 10/22/2020
Weiland Road Work Completed Installation of the storm sewer on the east side of the roadway up to Aptakisic has[...]
Project Update 10/22/2020
Work Completed Completed base asphalt paving for the future southbound lanes Switched southbound traffic onto the new lanes except at[...]
Project Update Video
Check out the video for an update of the project’s progress.