Weiland North
The project is approximately 45% complete.

Work Completed and Upcoming
Weiland Road

  • Traffic is currently driving on the new pavement on the east side of Weiland Rd and will remain like this through the winter
  • Storm Sewer work is expected to continue on the west side of Weiland Rd north of Thompson Blvd, as weather allows
  • Pavement Removal and Excavation for the roadway on the west side of Weiland Rd is expected to resume early Spring

Aptakisic Road

  • Traffic is currently driving on the new pavement on the north side of Aptakisic Rd
  • Curb and Gutter and Asphalt base was mostly completed on the south side of Aptakisic Rd which will be used to shift traffic in the Spring, so remaining work in the middle can be completed
  • Traffic Signal and Street Lighting foundation and conduit work is expected to continue, as weather allows