Project Updates - South Section: Lake Cook Road to Deerfield Parkway

Project Updates - North Section: Deerfield Parkway to Aptakisic Road

New Staging Pattern

22 Sep 2020

/

wpweiland

Traffic will be shifted to a new staging pattern on Weiland Road from Deerfield Parkway to Woodstone Drive tomorrow, Septembe ...

0
0

Project Update 9/17/20

17 Sep 2020

/

wpweiland

Work Completed The storm sewer installation, earth excavation and stone base have been completed for the future southbound la ...

0
0

Project Update 9/17/2020

17 Sep 2020

/

wpweiland

Work Completed Weiland Road - The contractor has completed the storm sewer up to Old Weiland Rd, installed street lighting an ...

0
0

Project Update 8/14/2020

14 Aug 2020

/

wpweiland

Work Completed Weiland Road - The stone base was installed and prepared for curb installation from Deerfield Parkway north to ...

0