Project Updates - South Section: Lake Cook Road to Deerfield Parkway

Project Updates - North Section: Deerfield Parkway to Aptakisic Road

Project Update 6/3/2020

03 Jun 2020

/

wpweiland

Last week the contractor completed excavation and placement of the stone base for the roadway on the east side.  The concrete ...

0
0

Project Update 5/19/2020

19 May 2020

/

wpweiland

Work continued on the concrete curb and asphalt pavement installations. The new pavement base has been installed from Woodsto ...

0
0

Project Update 6/3/2020

03 Jun 2020

/

wpweiland

Last week the contractor continued with removal of the curb, driveways, and sidewalks and began the installation of storm sew ...

0
0

Project Update 5/19/2020

19 May 2020

/

wpweiland

The contractor's progress has been slowed due to the recent rainfall.  The contractor has removed the majority of existing pa ...

0
0